The race for land for solar power projects in Northern Italy favours those who act first
English version of the release issued to the Italian press on 5 November 2026.
The location coefficients for FER X, restrictions on the use of agricultural land and grid constraints are making the search for solar power sites in Northern Italy increasingly targeted. Having engaged with over 50 developers since the summer, Solmeria has identified a key challenge: securing high-quality land before competitors do, without having to wait months to set up a local team. The proposed solution is targeted origination, with pre-qualified opportunities and remuneration linked to agreed development milestones.
Opportunities in the North require careful selection of areas
In the final FER X, the location-based coefficients applied to photovoltaic bids are zero in the North and Centre-North market zones. In other zones, the adjustments can reach 24.3 €/MWh in Calabria and 28.5 €/MWh in Sicily and Sardinia, depending on the power brackets and applicable zonal thresholds. These adjustments affect the auction ranking, not the winning bid price, thereby strengthening the incentive to develop projects in the most suitable areas of the North. [1]
The use of agricultural land is also subject to regional limits. For the types of project in question, Lombardy sets a standard threshold of 0.8 per cent of the regional utilised agricultural area (UAA) and 3 per cent of the UAA of each municipality. Piedmont limits agricultural land classifiable as suitable areas to 0.8 per cent of the regional agricultural area; Emilia-Romagna sets a range of between 0.8 per cent and 1.5 per cent. The calculation may include projects that have already been authorised, even before work has commenced, making it all the more important to identify sites in good time. [2]
Network constraints make the search even more selective. Of the 755 primary substations in the North analysed by Solmeria, one in five has at least one saturated HV/MV section. These indicators guide the initial assessment of sites; however, the availability of connection capacity must be verified for each project. [3]
160 of the 755 primary substations in the North analysed (21.2 per cent) have at least one saturated HV/MV section.
A suitable site combines land-use conditions that are compatible with the project, potential transport links that warrant further investigation, and a landowner who is open to discussion. Identifying such a site at an early stage gives developers an advantage when assessing the viability of the project and commencing negotiations.
It takes months to put a team together, whereas websites attract interest within a few days
Among the developers Solmeria has been in contact with, several now base their search on specific connection points, looking for land in the vicinity. The challenge lies in turning these targets into a stream of opportunities while the local origination team is still being set up. [4]
Launching a search for land in a new region involves recruiting and training a team, building a network of contacts and developing relationships with landowners. Fixed costs are incurred before a steady stream of opportunities can be expected. According to Solmeria’s estimates, starting from scratch, it takes between nine and twelve months to get an origination structure up and running in a new area. [4]
We have refocused our search towards the north and know which primary substations we want to concentrate on. What we’re missing is a team on the ground: it takes months to recruit one, and in the meantime, the sites we’re interested in are already the subject of negotiations with others. A request to connect to the grid no longer guarantees anything; what matters is getting to the right plot of land and its owner before anyone else does.
Competition for land suitable for solar power is already evident. At the end of October, Solmeria published a listing for a large site in northern Italy, situated near a main substation and with an owner open to discussion. Five developers requested information about the site within six days. [4]
For developers, the message is clear: when it comes to prime sites, you need to act straight away. Those who are the first to enter into substantive discussions with the owner have a head start; those who wait risk finding that negotiations are already underway.
Operators entering a new area, as well as those already established there, therefore need to gain access to suitable sites first and expand their geographical coverage, without having to wait for new staff to be recruited.
Targeted origination with remuneration linked to development milestones
The Solmeria model, developed in France since 2020, is based on a network of over 80 partners, including developers and investors, and on over 4 GWp of projects in the partners’ development portfolios. Since the summer, ten developers have signed up to the Italian scheme. [4]
The project is planned in collaboration with each developer, defining regions, local authorities, connection points, site sizes and technologies. Once the criteria have been agreed, the search can begin within the same week. The pre-qualification process involves analysing land-use regulations and restrictions, as well as an initial assessment of the network. Property owners are briefed on the options for sale, lease or the granting of a building lease, as well as the project’s stages and timelines, so that developers can engage in substantive discussions with well-informed stakeholders.
According to the company’s figures, Solmeria currently generates around ten new pre-qualified opportunities per week in Italy, mainly in the North and Centre. Since June, it has received over 900 enquiries from landowners in Italy. Of the contacts made by the company, around one in four results, according to internal monitoring, in a published opportunity. [4]
Developers can access this service without a subscription and without incurring the fixed costs involved in setting up an additional land-scouting team. Under the milestone-based model, Solmeria supports the developer in negotiations with the landowner and is remunerated upon the achievement of agreed milestones, starting with the first land agreement. A portion of the origination cost thus becomes variable, while in-house teams gain an additional channel to expand their project portfolio.
High-quality plots of land can attract interest from several developers within a matter of days, whereas it takes months to recruit a team. Developers need to be able to act when a suitable opportunity arises. Solmeria acts as the catalyst in this initial phase: targeted origination, owners ready for discussion, and fees linked to the project’s progress.
Sources
- [1] MASE, Directorial Decree No. 93 of 2 October 2026, Article 3; GSE, FER X final version. Location-based adjustments for photovoltaic projects depend on the market zone, power brackets and applicable zonal thresholds. They affect the auction ranking, not the award price.
- [2] Lombardy: Regional Law No. 10 of 21 May 2026, Article 2 (regional and local thresholds for the use of agricultural land, subject to the exceptions provided for by law). Piedmont: Regional Law No. 15 of 28 July 2026, Article 3. Emilia-Romagna: Regional Law No. 15 of 27 October 2026, Article 3, amending Regional Law No. 5/2026. The rules differ between regions: in Emilia-Romagna, the loss of ‘suitable area’ status does not amount to a general ban on further development.
- [3] Solmeria analysis of public data from e-distribuzione extracted on 23 October 2026: 755 primary substations and 1,389 HV/MV sections; 160 substations (21.2 per cent) with at least one saturated section. Scope: available data relating to the e-distribuzione network in Northern Italy, excluding the province of Turin and excluding coverage by other operators. The indicator does not confirm the availability of connection capacity nor does it imply a refusal of connection.
- [4] Solmeria company data provided for this press release and updated as at 4 November 2026. Comparisons with developers represent feedback from the field, not a statistically representative survey. The weekly volume of opportunities and the conversion rate of contacts reached are current indicators reported by the company; the conversion rate is not calculated using all incoming enquiries as its denominator. Published opportunities remain subject to verification by the developer. Sign-ups in Italy refer to acceptance of the platform’s terms and conditions. The five enquiries received over a six-day period concerned additional information, without any contractual commitment or automatic site allocation. The nine- to twelve-month period is an estimate of the time required for commercial and organisational start-up, not of the time required for authorisation. The figures relating to France refer to projects under development and to partners with whom the company has collaborated over time, not to capacity that has already come on stream.
About Solmeria
Solmeria is a land origination platform which, since 2020, has been connecting landowners with solar developers. Solmeria identifies, assesses and proposes land for solar, agrivoltaic and energy storage projects, preparing landowners for discussions with developers. It operates in France and, from summer 2026, will also operate in Italy.