BESS permitting in France: prior declaration, building permit and ICPE
In France, a BESS under 5 m² needs no planning consent. Up to 20 m² of footprint, a prior declaration (one month) suffices; above, a building permit (three months), issued by the prefect. Above 600 kW of charging power, an ICPE declaration applies. Under 1 MW, Enedis classes the unit as type A. HTA caps at 12 MW, 17 MW by derogation.
Data as of September 30, 2026.
What each threshold changes
A few figures decide how heavy a project is. They do not all measure the same thing: surface area, charging power, unit power. Knowing them means knowing where to position your project.
Rule
Threshold
What it changes
Text
Planning consent
5 m² · 20 m²
Nothing to file under 5 m². Prior declaration (DP) up to 20 m² of footprint, processed in 1 month. Building permit (PC) above, processed in 3 months.
Urban planning code, R.421-2, R.421-9, R.423-23
Environmental classification (ICPE)
600 kW
Declaration above 600 kW of charging power.
Heading 2925-2
Enedis technical category
1 MW
Under 1 MW, two fewer certificates and no remote control unit.
Enedis NMO-RES_026E
Low voltage
250 kVA
Above, HTA connection with a private delivery substation.
Decree of 9 June 2020
HTA ceiling
12 MW · 17 MW
17 MW by derogation, with a dedicated feeder to the primary substation. Above, HTB.
Decree of 9 June 2020
Keep reading: get the full study
25-page PDF, sent by email.
Why so many batteries are exactly 1 MW
A unit of about 1 MW fits in a single compact container. It is the format most likely to stay under 20 m² of footprint, delivery substation included, and therefore to need only a prior declaration. And under 1 MW, Enedis classes the unit in the lightest category ("type A"). The register shows it: the fleet’s standard format went from 1,250 kW to 1,239 kW, and the first units of 990 to 999 kW appeared in 2026.
The 20 m² threshold is about surface, not power. Footprint is the ground projection of all the project’s structures. The delivery substation creates one: the prudent reading is to add it to the container’s. A 15 m² container plus a delivery substation then exceeds 20 m², and a building permit is needed. Have the permitting authority confirm before filing.
The prefect issues the permit for an energy storage facility, not the mayor.
In agricultural or natural zones, the question is whether the battery counts as public-interest equipment. Several 2026 decisions point that way.
Recent case law. The Nantes administrative court of appeal applied the Littoral (coastal) law to a battery for the first time (2 November 2026). The Orléans administrative court suspended a permit refusal in an agricultural zone (23 October 2026).
Sources: French urban planning code; ICPE nomenclature, heading 2925; Enedis notes NMO-RES_026E and NMO-RES_032E; decree of 9 June 2020; national register at 30 September 2026.
Solmeria Insights. Analysis based on the national register, Enedis and RTE grid data, and the plots offered to Solmeria.