BESS permitting in France: prior declaration, building permit and ICPE

In France, a BESS under 5 m² needs no planning consent. Up to 20 m² of footprint, a prior declaration (one month) suffices; above, a building permit (three months), issued by the prefect. Above 600 kW of charging power, an ICPE declaration applies. Under 1 MW, Enedis classes the unit as type A. HTA caps at 12 MW, 17 MW by derogation.

Data as of September 30, 2026.

20 m² of footprint: above it, a building permit

What each threshold changes

A few figures decide how heavy a project is. They do not all measure the same thing: surface area, charging power, unit power. Knowing them means knowing where to position your project.

RuleThresholdWhat it changesText
Planning consent5 m² · 20 m²Nothing to file under 5 m². Prior declaration (DP) up to 20 m² of footprint, processed in 1 month. Building permit (PC) above, processed in 3 months.Urban planning code, R.421-2, R.421-9, R.423-23
Environmental classification (ICPE)600 kWDeclaration above 600 kW of charging power.Heading 2925-2
Enedis technical category1 MWUnder 1 MW, two fewer certificates and no remote control unit.Enedis NMO-RES_026E
Low voltage250 kVAAbove, HTA connection with a private delivery substation.Decree of 9 June 2020
HTA ceiling12 MW · 17 MW17 MW by derogation, with a dedicated feeder to the primary substation. Above, HTB.Decree of 9 June 2020