BESS returns and project prices in France: costs, payback and value per MW
In France, an HTA battery needs about €100k per MW per year to earn 8% on capital over fifteen years. A 2.5 MW Small BESS costs about €625k per MW (€1.6m) and pays back in 2.5 years at current French revenues, 4 years at German levels, 6 to 7 on the forecast path. Ready-to-build projects sell for €60k to €90k per MW.
Data as of September 30, 2026.
What a battery costs, and how much it must earn
Every profitability calculation depends on a revenue forecast nobody controls. So we ask the question differently: how much must a battery earn to be worth its cost?
Net revenue needed each year to pay 8% on capital
Micro LV 0.25 MW≈ 180
Small 1 MW≈ 110
Small 2.5 MW≈ 100
Small 5 MW≈ 100
Large 12 MW≈ 100
Maxi 100 MW≈ 90
2-hour battery, in €k per MW per year, over fifteen years. Forecasters expect about €100k on average over the period. Solmeria estimates.
Years to pay back a 2.5 MW Small BESS
Current French revenues≈ 2.5 years
Current German revenues≈ 4 years
Forecast trajectory in France≈ 6 to 7 years
Depending on revenue level, assumed constant. Gross revenues of a 2-hour battery (Modo Energy), less 15% aggregation commission and operating costs, with no power limitation (an ORA-MP connection would reduce these revenues). Solmeria estimates.
At the current French revenue level, every segment pays back in two to four years. But this level will not last: at today’s German level it takes four years, and on the trajectory forecast for France, six to seven. The window is real, but short.
Cost, required revenue and payback by segment
Segment
Cost per MW
Project cost
Required revenue, per MW per year
Payback, French revenues
Payback, German revenues
Micro LV 0.25 MW
≈ €525k
€0.13m
≈ €180k
≈ 3.3 years
≈ 8 years
Small 1 MW
≈ €690k
€0.7m
≈ €110k
≈ 2.8 years
≈ 4.5 years
Small 2.5 MW
≈ €625k
€1.6m
≈ €100k
≈ 2.5 years
≈ 4 years
Small 5 MW
≈ €600k
€3m
≈ €100k
≈ 2.4 years
≈ 4 years
Large 12 MW
≈ €620k
€7.5m
≈ €100k
≈ 2.5 years
≈ 4 years
Maxi 100 MW
≈ €575k
€58m
≈ €90k
≈ 2.3 years
≈ 3.7 years
2-hour battery, connection and development included. Solmeria estimates, cross-checked against a 50 MW project with a published cost (€573k/MW).
Small BESS of 2.5 to 5 MW sits at the same level as large projects. Two reasons: a short connection on an existing line costs less per MW than a dedicated feeder to the primary substation, and the project goes into service six months to a year earlier, on revenues that fall year after year. The gap with Large BESS stays within the margin of error: read "comparable", not "better".
What return to target? Depending on the revenue contract, investors target a return on equity of 9 to 11% with a fixed-price lease (tolling), 11 to 13% with a revenue floor, and over 13% when fully exposed to the market (Tevali Partners and Forsyt Energy). The larger the installed fleet grows, the longer payback gets: the commissioning date makes the return.
Keep reading: get the full study
25-page PDF, sent by email.
Observed costs, in France and elsewhere
Project
Construction cost
Development cost
France, 50 MW, 2 hours, transmission network
€573k per MW (published)
Not published
France, portfolio of 3.4 to 12 MW, 2 hours, under building permit
Not published
About €30k per MW, published provisional budget
France, 2.5 MW Small BESS
About €625k per MW (Solmeria estimate)
Less per site: lighter studies, often no building permit
Italy, large 4-hour projects
€430k to €690k per MW (published)
€5k to €18k per MW (published)
The only published French figure is a provisional budget: €1.5m raised to take six projects under building permit through to ready to build, environmental studies included. It does not measure the actual cost of a Small BESS, whose file is lighter. The gap with the resale value, €60k to €90k per MW, is the developer’s margin, before failed projects.
What a ready-to-build project is worth
A developer can sell a project before building it. In France, a ready-to-build project currently sells for €60,000 to €90,000 per MW, against about €20,000 a few years ago. The gap with the development cost is the developer’s margin.
Value of a ready-to-build BESS project
France, today60 to 90
France, a few years ago≈ 20
Published French portfolio80
Italy, 36 kV projects≈ 80
Italy, very large project30 to 45
€k per MW, for a project with land signed, permit obtained and connection accepted. France: Solmeria market analysis and a published portfolio of six projects of 3.4 to 12 MW. Italy: published portfolios.
Before that stage, value is far more uncertain: without a planning permit, no reference price exists.
What the landowner receives
Segment
Annual lease
Leased area
Maxi
€1k per MW or less, or a flat annual rent on the footprint
About 1 ha
Large
About €1k per MW, so €15k to €20k for 16 MW
1,000 to 2,000 m²
Small
€1k to €2k per MW
150 to 500 m² per MW
Micro
About €1k per site, up to €3k to €5k
5 to 20 m²
The lease falls with size. The larger the project, the lower the lease per MW. A floor of about €1,000 per year per site applies whatever the power.
Flat or per MW. Developers prefer to lease an area at a flat rate. For the landowner, a lease indexed on the power actually obtained at connection is safer.
A renewable 8 to 9-year commercial lease, not a long-term emphyteutic lease as for ground-mounted solar.
Less per MW than solar, but far more per m². The battery takes a few hundred m² instead of several hectares.
Sources: Solmeria estimates; Modo Energy; Enerfip crowdfunding project sheets (cost of a 50 MW project, value and development cost of a 3.4 to 12 MW portfolio, Italian portfolios); Solmeria market analysis, 2026.
Solmeria Insights. Analysis based on the national register, Enedis and RTE grid data, and the plots offered to Solmeria.